BUS 375 WK 2 Chapter 1,2 Quiz – All Possible Questions

CHAPTER 1:

(E) 1. In today’s market, which of the following industries appears to have a need for project managementA. Aerospace & defense
B. Construction
C. Information systems
D. All industries have a need for project management

(M) 2. Which of the following is not one of the PMBOKa Guide’s five process groups A. Feasibility studies
B. Planning
C. Execution
D. Closure

(E) 3. Which of the following is normally not one of the traditional components of the triple constraintA. Within time
B. Within cost
C. Within performance (Scope, technology or quality)
D. Accepted by the customer

(M) 4. Which of the following is a potential benefit of using project managementA. Maximization of continuous reporting
B. No need for identification of functional responsibilities
C. Identification of time limits for scheduling
D. No need for a project management methodology

(E) 5. Which of the following functions of classical management is generally not performed by the project managerA. Planning
B. Organizing
C. Staffing
D. Controlling

(M) 6. Which of the following three types of deliverables discussed in the book would be used to classify the final report that must be presented to the customer at the end of the projectA. Hardware deliverables
B. Software deliverables
C. Interim deliverables
D. Validation deliverables

(E) 7. Which of the following is not an organizational stakeholderA. Executive officers
B. Unions
C. Employees
D. Customers

(E) 8. Which of the following is not a…